Open for business: Architects craft thoughtful design for Canadian Canoe Museum
Open for business: Architects craft thoughtful design for Canadian Canoe Museum
Former EllisDon CEO Geoff Smith heavily involved in development
Canoe collection storage ‘weaved into the flow of the building’
The stock of housing is falling exactly when we need it to rise
ROADS, PARKS AND FORESTRY OFFICE RENOVATION PHASE 2 $500,000 est
TENANT FIT OUT CONSTRUCTION FOR THE RICHMOND HILL OFFICE SPACE REDUCTION $300,000 est
POOL BOILER REPLACEMENT AT MISSISSAUGA VALLEY COMMUNITY CENTRE $100,000 est
SACRED HEART ELEMENTARY SCHOOL RENOVATIONS: BARRIER-FREE WASHROOMS $100,000 est
THORNHILL COMMUNITY CENTRE’S ENERGY AND GHG RETROFIT $2,000,000 est
EXPANSION OF DIALYSIS CAPACITY AT CENTENARY HOSPITAL $10,500,000 est
RICK MACLEISH MEMORIAL COMMUNITY CENTER FLAT ROOF REPLACEMENT $200,000 est
IPA-IHP SYSTEM REPLACEMENT ABATEMENT AT C.R. MARCHANT MS $50,000 est
LED REPLACEMENT AT GARNET A WILLIAMS COMMUNITY CENTRE $200,000 est
GENERAL CONTRACTING SERVICES FOR THE LORNE PARK LIBRARY - ROOF AND MECHANICAL RENEWAL $300,000 est
ORANGEVILLE CHRISTIAN SCHOOL ADDITION - SUB TRADES $2,400,000 est
OFFICE HVAC UPGRADES AT TOMKEN ROAD PUBLIC SCHOOL $250,000 est
TOWN HALL CAFETERIA INTO FLEXIBLE OFFICE SPACE RENOVATIONS $200,000 est
GYM A FLOOR REPLACEMENT AND WEST GYM RE-LINING AT THORNCLIFFE PARK PUBLIC SCHOOL $200,000 est
RFP CONTRACTOR - ALEXANDRA PARK PHASE 2A - SITE 3 & 16 - MASONRY (TCHC) $60,000,000 est
EXTERIOR WALL REPAIRS AT COLE LMENTAIRE LA MOSAQUE $200,000 est
VICTORIA HARBOUR WASTEWATER TREATMENT PLANT - PHASE 2 UPGRADES $2,000,000 est
BARRIE NORTH COLLEGIATE INSTITUTE BUILDING RENOVATIONS $500,000 est
LIBRARY AC AT DR. ROBERT THORNTON PUBLIC SCHOOL $200,000 est
WINDOW AND PATIO DOOR REPLACEMENTS AT ROSE TOWN APARTMENT COMPLEX FOR SENIORS $250,000 est
PHYSICS COLLABORATIVE RESEARCH LEARNING CENTRE RENOVATION $500,000 est
UNNAMED NORTH OSHAWA SECONDARY SCHOOL CONSTRUCTION $45,000,000 est
UNNAMED PICKERING SEATON PUBLIC SCHOOL CONSTRUCTION $19,300,000 est
FIRE SAFETY SYSTEM UPGRADE - 18106 YONGE STREET $200,000 est
SHINGLE ROOF REPLACEMENT OF THE SALT DOME AT THE BROOKVILLE OPERATIONS YARD $800,000 est
PREQUALIFICATION #2 TRADES - NEW TYNDALL LONG-TERM CARE FACILITY / MISSISSAUGA $67,000,000 est
ALEXANDRA PARK PHASE 2A- SITE 3 & 16 - WOOD STAIRS AND RAILING (TCHC) $60,000,000 est
PROPOSAL - EMERY COLLEGIATE INSTITUTE ARTIFICIAL TURF $700,000 est
RFQ CONTRACTOR - HARVIE HILL GENERAL CONTRACTOR PRE-QUALIFICATION $12,000,000 est
DEMOLITION AND RECONSTRUCTION OF OLD LANGSTAFF BRIDGE $500,000 est
PARKING LOT LIGHT REPLACEMENT AT FIRE STATION 94 $100,000 est
BASEMENT FLOODING PROTECTION PROGRAM, PHASE 4, ASSIGNMENTS 19-06D $1,000,000 est
BIORETENTION CELL CURB INLET INSTALLATION AND LID MAINTENANCE $200,000 est
WATERMAIN REPLACEMENT ON MOUNT HOPE ROAD, TOWN OF CALEDON $2,000,000 est
WOODBRIDGE YARD,INTERSITE PLACE AND MILLWOOD PARKWAY CULVERT REMOVALS AND REPLACEMENTS $900,000 est
BROCK PARK AND GROVE PARK NEIGHBORHOOD RESURFACING $400,000 est
HIGHWAY 401 - GRADING, HOT MIX PAVING, STRUCTURES REHABILITATION $4,500,000 est
CIRCLE COMMUNITY LANDTRUST - WINDOW & DOOR REPLACEMENTS $500,000 est
CULVERT WORK AT VARIOUS LOCATIONS IN THE REGION OF YORK $900,000 est
BROCK PARK AND GROVE PARK NEIGHBORHOOD RESURFACING $400,000 est
PROPOSAL - EMERY COLLEGIATE INSTITUTE ARTIFICIAL TURF $700,000 est
T11PU24273-C60-25-WILSON YARD FIRE ROUTE ON-GRADE PAVING REHABILITATION $8,500,000 est
OUT FOR TENDER Building KENNER COLLEGIATE VOCATIONAL INSTITUTE ROOFING $300,000 est
RFQ CONTRACTOR - FAMILY RECREATION AREA WITHIN NORTH MAPLE REGIONAL PARK $20,000,000 est
PAVEMENT LINE MARKING PROGRAM ON BEHALF OF THE HALTON CO-OPERATIVE PURCHASING GROUP $50,000 est
CONSTRUCTION OF LAY-BY LANE AT AURORA HEIGHTS PUBLIC SCHOOL $100,000 est
CIRCLE COMMUNITY LANDTRUST - WINDOW & DOOR REPLACEMENTS $500,000 est
ST. JOSEPH-SCOLLARD HALL CATHOLIC SECONDARY SCHOOL - INTERIOR RENOVATIONS $100,000 est
OTONABEE VALLEY PUBLIC SCHOOL ACCESSIBLE DOOR UPGRADE $100,000 est
IWSD/IS/DCMB CP00124 HURDMAN BRIDGE PUMP STATION $5,000,000 est
TEMAGAMI PUBLIC SCHOOL EXTERIOR WINDOW REPLACEMENT $300,000 est
EXTERIOR RESTORATION AND WATER MANAGEMENT PROJECT $500,000 est
PERRY MINE REHABILITATION - 47 NORTH SHORE LANE, MADOC $500,000 est
IWSD/IS/DCFB CF000361 WEST CARLETON SALT DOME - FOUNDATION WALL REPAIRS $200,000 est
RENOVATION OF INDIGENOUS WORK AREA (NICH ROOM) AT NORTH HASTINGS HIGH SCHOOL $200,000 est
CORDOVA OUTDOOR RINK PREPARATION AND INSTALLATION OF BOARD SYSTEM $100,000 est
THE PINES LONG-TERM CARE HOME - SPA RENOVATIONS $100,000 est
RFQ CONTRACTOR - NEW OPERATING ROOM NHH - NORTHUMBERLAND HILLS HOSPITAL $500,000 est
CORDOVA OUTDOOR RINK PREPARATION AND INSTALLATION OF BOARD SYSTEM $100,000 est
PRINCESS STREET & COLLINS BAY ROAD ACTIVE TRANSPORTATION IMPROVEMENTS - PHASE 2 $200,000 est
MONTREAL ROAD BICYCLE PATH RETAINING WALL REPLACEMENT $200,000 est
PRINCESS STREET & COLLINS BAY ROAD ACTIVE TRANSPORTATION IMPROVEMENTS - PHASE 2 $200,000 est
THOMAS A STEWART SECONDARY SCHOOL TURF REPAIR $2,000,000 est
PAVEMENT REHABILITATION AT 2825 KING ST E. HAMILTON $400,000 est
DEVELOPMENT OF FAIRVIEW AND MARSHALL’S BAY PARK $500,000 est
HIGHWAY 630 - GRADING, DRAINAGE, GRANULAR BASE, HOT MIX PAVING AND STRUCTURAL $2,000,000 est
LAURIE AVENUE SEWAGE PUMPING STATION AND FORCEMAIN UPGRADE $3,946,000 est
WESTMINSTER SECONDARY SCHOOL ROOFTOP UNIT REPLACEMENTS $100,000 est
SUPPLY OF A STANDBY GENERATOR FOR THE ADELAIDE WASTEWATER TREATMENT PLANT $200,000 est
PAULINE JOHNSON ELEMENTARY SCHOOL WASHROOM RENOVATION $100,000 est
TECUMSEH ARENA INTERIOR REFRESH AT 12021 MCNORTON ST $250,000 est
ROOF REPLACEMENT AND MUA INSTALLATION 263 SPEEDVALE AVENUE EAST $500,000 est
PARKDALE ELEMENTARY SCHOOL GYM & MAIN ENTRANCE RENOVATION PROJECT $500,000 est
ROBERTSON SCHOOL - MAIN BUILDING ACCESSIBILITY UPGRADES $1,500,000 est
RFP CONTRACTOR - TOWN OF TECUMSEH SWIMMING POOL RESURFACING 2024 $50,000 est
ROOF & DRAINAGE REPAIRS - ALUMNI STADIUM BUILDING 178 $500,000 est
RFP - CONSTRUCTION MANAGER FOR GUELPH TRANSIT AND FLEET SERVICES FACILITY $30,000,000 est
WESTMINSTER SECONDARY SCHOOL ROOFTOP UNIT REPLACEMENTS $100,000 est
SUPPLY AND INSTALLATION OF RIVER RUN CENTRE THEATRE SEATING $100,000 est
PATROL SHOP ACCESSIBILITY UPGRADES/ GAS DETECTION/GENERATOR INSTALLATION $300,000 est
SIR ALLAN MACNAB SECONDARY SCHOOL CORRIDOR RENOVATION $200,000 est
SOUTH HURON DISTRICT HIGH SCHOOL VARIOUS UPGRADES $790,000 est
PROPOSAL - 200 KING STREET RESIDENCE PARKING GARAGE REPAIRS $300,000 est
RFP - CONSTRUCTION MANAGER FOR GUELPH TRANSIT AND FLEET SERVICES FACILITY $30,000,000 est
SUPPLY OF SWITCHGEAR FOR THE ADELAIDE WASTEWATER TREATMENT PLANT $200,000 est
ALLANBURG COMMUNITY CENTRE RENOVATION CHILD CARE CENTRE DESIGN $400,000 est
WATERMAIN REPLACEMENT - DAVIS STREET, HOMEWOOD AVE., BERKLEY AVENUE AND WEST STREET $6,000,000 est
ST. ANNE CATHOLIC HIGH SCHOOL WASHROOM UPGRADES $100,000 est
BILL BURGOYNE ARENA - CLADDING, LIGHTING, HVAC AND FOUNDATION REPAIRS $750,000 est
ST. ANTHONY CATHOLIC ELEMENTARY SCHOOL - WASHROOM UPGRADES $300,000 est
UOFG - SCIENCE COMPLEX - LAB 1401 RENO UNIVERSITY OF GUELPH P , BUILDING #140 $200,000 est
WATERMAIN REPLACEMENT - DAVIS STREET, HOMEWOOD AVE., BERKLEY AVENUE AND WEST STREET $6,000,000 est
CLASSROOM RENOVATIONS - WATERFORD DISTRICT HIGH SCHOOL $200,000 est
GREY ROOTS MUSEUM AND ARCHIVE - AHU REFURBISHMENT $300,000 est
REMEDIATION & DEMOLITION OF RESIDENTIAL BUILDING, POINT EDWARD $100,000 est
TRAIL AND ASSOCIATED WORKS CAMBRIDGE WEST - CACHET SUBDIVISION $500,000 est
LACASSE PARK PARKING AND TRAIL IMPROVEMENT PROJECT $300,000 est
RFP D/B - DESIGN, SUPPLY AND INSTALLATION OF MILITARY MEMORIALS $100,000 est
SPRINGBANK DAM DECOMMISSIONING AND BANK RESTORATION $500,000 est
SIDEWALK REPLACEMENT AT THE TOWNSHIP OF NORWICH $100,000 est
ASPHALT 2024 TENDER $500,000 est STRATHROY, Middlesex, ON Multiple Locations, Strathroy, N7G 1V5
LACASSE PARK PARKING AND TRAIL IMPROVEMENT PROJECT $300,000 est
WATERMAIN REPLACEMENT - DAVIS STREET, HOMEWOOD AVE., BERKLEY AVENUE AND WEST STREET $6,000,000 est
CULVERT REPLACEMENT COUNTY ROAD 18 OVER LONG MARSH DRAIN $900,000 est
NORTHERN COLLEGE INNOVATION HUB KIRKLAND LAKE CAMPUS $300,000 est
MATTAGAMI RIVER BOAT LAUNCH - PIER AND RETAINING WALL REPAIRS $200,000 est
BUILDING RESTORATION AND REPAIRS AT CENTENNIAL PARK - MOOSE FACTORY $300,000 est
YONGE AT WELLESLEY STATION CONDOMINIUM, RETAIL BUILDING $82,000,000 est
ROOF REPLACEMENT AT CHANCELLOR COMMUNITY CENTRE $929,350 est
FENCING CORRECTIVE REPAIRS AND NEW INSTALLATIONS $200,000 est
NORTH GRENVILLE DISTRICT HIGH SCHOOL STEEL STORAGE GARAGE $198,965 est
600 VILLAGE PARKWAY - PARKING LOT CURBS & PAVING $109,200 est
STORMWATER MANAGEMENT FACILITY (SWMF) SEDIMENT REMOVAL $1,499,250 est
NEW COLUMBARIUM FEATURE AT TRAFALGAR LAWN CEMETERY $100,000 est
EXTERIOR DOOR REPLACEMENT PROJECT AT BLESSED TRINITY CATHOLIC SCHOOL $100,000 est
IWSD/IS/DCFB CF00528 ALFRED TAYLOR RECREATION FACILITY - TENNIS COURT RENEWAL $248,387 est
SUPPLY AND INSTALLATION OF A NEW ROOF SYSTEM AT THE CORNWALL CIVIC COMPLEX $974,368 est
IWSD/IS/DCMB CP000741 BILBERRY AND SOUTHMORE TRAFFIC CALMING $508,309 est
Building MITCHELL DISTRICT HIGH SCHOOL WASHROOMS, DOORS AND SCREENS UPGRADES $200,000 est
REHABILITATION OF COUNTY STRUCTURE B181 (PETER BLACK BRIDGE) $1,282,480 est
STEWARD PARK AND LOYALIST PARK GAZEBO CONSTRUCTION $200,000 est
12TH CONCESSION ROAD BRIDGE REPAIR $78,677 est WESTPORT, Leeds and Grenville, ON
JOINT-ELEMENTARY SCHOOL AT INTERSECTION OF WHITHORN CRESCENT AND MACLACHLAN AVENUE $26,810,000 est
SLURRY SEALING $200,000 est SOUTH MOUNTAIN, Stormont; Dundas and Glengarry, ON
FILTER UNDERDRAIN INSTALLATION TRENTON WATER TREATMENT PLANT $637,720 est
YORK BOULEVARD AND CANNON STREET URBANIZATION AND 500MM TRUNK WATERMAIN INSTALLATION $9,687,000 est
CENTENNIAL BOTANICAL CONSERVATORY PHASE 2 RENEWAL $6,881,950 est
STAGE 2 - TIP TOWER GUARDRAIL REPLACEMENT AND REPAIRS, POINT PELEE NATIONAL PARK $789,305 est
JOINT-ELEMENTARY SCHOOL AT INTERSECTION OF WHITHORN CRESCENT AND MACLACHLAN AVENUE $26,810,000 est
WATERLOO LANDFILL WEST SIDE MANHOLE SLOPE RESTORATION $1,277,684 est
RIDGE ROAD EAST CULVERT REPLACEMENT STRUCTURE NO. BRDG002051 $383,463 est
RFP - BROOKE CENTRAL PUBLIC SCHOOL ROOF REPLACEMENT $200,000 est